Thursday 1 November 2007

Forthcoming Activities

Over the next 5 weeks the new coarse screens are to be installed along with the associated screw conveyors and access structures.
The temporary screens installed in the lamellas are to be removed this week.
After alteration and refurbishment at Adams they will be returned to site and installed in the existing FFT chambers to screen FFT flows.
On the east side of the inlet works a tarmac hardstanding area will be constructed to allow the delivery and removal of screenings skips to the new megawasher area.